| Gibbs Construction |
11,853,868.63 |
10,798,988.23 |
Per change order 3 on 1/27/2025 |
| Architects Beazley-Moilere |
748,219.00 |
691,511.79 |
8.1007% of const. budget |
| Landry Management Consultants |
596,590.00 |
515,906.00 |
Per Contract Ammendment 2 on 10/04/2023 |
| Beverly Construction |
690,473.28 |
690,473.27 |
Per change order 3 on 12/13/2021 |
| Mike Munna Construction |
90,800.00 |
73,450.00 |
Per change orders 1+2 71,950 +1 8,850 3 on 11/27/2019 |
| Pedigo Enterprises |
11,800.00 |
12,850.00 |
Per amendment 2 on 08/22/2022 |
| The Beta Group |
0 |
69,141.50 |
No contract |
| St. Bernard Parish Clerk of Court |
0 |
4,050.00 |
No contract |
| All South Consulting Engineers |
0 |
14,850.00 |
No contract |
| KLS Group |
0 |
6,300.00 |
No contract |
| Pot-O-Gold Waste Services |
0 |
23,864.00 |
No contract |
| Dison Enterprises |
0 |
1,200.00 |
No contract |
| St. Bernard Voice Newspaper |
0 |
613.50 |
No contract |
| St. Bernard Parish Government |
0 |
0.00 |
No contract |
Totals: |
13,991,750.91 |
12,903,198.29 |