SBPL Header
 
   

New Library Budget vs Actual

As of 11/20/2024


VendorBudgetedActualComment
Gibbs Construction 11,783,055.17 7,823,139.40 Per change order 2 on 11/14/2024
Architects Beazley-Moilere 748,219.00 691,511.79 8.1007% of const. budget
Landry Management Consultants 596,590.00 308,810.00 Per Contract Ammendment 2 on 10/04/2023
Beverly Construction 690,473.28 690,473.27 Per change order 3 on 12/13/2021
Mike Munna Construction 90,800.00 73,450.00 Per change orders 1+2 71,950 +1 8,850 3 on 11/27/2019
Pedigo Enterprises 11,800.00 12,850.00 Per amendment 2 on 08/22/2022
The Beta Group 0 59,129.70 No contract
St. Bernard Parish Clerk of Court 0 3,275.00 No contract
All South Consulting Engineers 0 14,850.00 No contract
KLS Group 0 6,300.00 No contract
Pot-O-Gold Waste Services 0 23,864.00 No contract
Dison Enterprises 0 1,200.00 No contract
St. Bernard Voice Newspaper 0 613.50 No contract
St. Bernard Parish Government 0 0.00 No contract

Totals:

13,920,937.45

9,709,466.66