| Jul. 19, 2019 | Land cleared of trees | |
| May. 12, 2020 | Surcharge sand placed for settlement | |
| Jun. 6, 2023 | Construction bid awarded | |
| Oct. 3, 2023 | Groundbreaking ceremony
| |
| Oct. 9, 2023 | Construction begins - sand removal | |
| Oct. 23, 2023 | Test pilings | |
| Dec. 11, 2023 | Drill final pilings
| |
| Jan. 15 2024 | Preparing foundation
| |
| Mar. 13, 2024 | Steel Structure Work | |
| May 6, 2024 | Insulation/Drainage Work | |
| July 8, 2024 | Brick laying | |
| Aug. 1, 2024 | Exterior Work | |
| Aug. 21, 2024 | Inside studs and drywall | |
| Sept. 18, 2024 | Parking Lot | |
| Oct. 23, 2024 | Windows | |
| Dec. 12, 2024 | Sidewalk | |
| Jan. 6, 2025 | Interior Work | |
| Jan. 20, 2025 | Landscaping | |
| Mar. 31, 2025 | Substantial Completion (45 days punch list) |